Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
To begin, Deep South received a reactor from the ship of origin and transported it via barge to a petrochemical facility up river. Using Goldhofer SPMTs, Deep South off-loaded the vessel from the barge and negotiated very tight turns and low pipe racks with minimum clearance to get it to the final off-loading location. Five-hundred-ton gantries were used to off-load to temporary supports.
Deep South modified the 1,500-ton VersaCrane TC-24000 specifically for this project to accommodate a very tight tail swing requirement. The vessel weighed 420,000 pounds, measured 100’ long and was lifted using 200’ of boom at a 95’ radius. Scheuerle SPMTs were used with the tailing frame to tail the load due to space constraints.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weighed 420,000 Pounds
- Vessel Measured 100’ Long
- VersaCrane was 200’ of Boom at a 95’ Radius
Related Projects
A Technical Towering Roll, Move, and Lift
View Project
A Technical Towering Roll, Move, and Lift
As part of a complex project for a refinery, the Deep South team was tasked with receiving, transporting and lifting a 114’-7” x 33’-5” x 39’-10” vacuum tower weighing in excess of one million pounds. This multi-step project required considerable planning, technology and creative thinking.
Managing the Weight of Expectations with Self-Deploying Bridge System
View Project
Managing the Weight of Expectations with Self-Deploying Bridge System
Transporting a 225,000-pound transformer over a bridge with a 30-ton weight limit would typically require the support of multiple assist cranes. With time and space constraints, a Louisiana-based heavy haul company teamed with Deep South to come up with alternative transport possibilities to manage the weight-limited bridge.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.